February 2026 
The project involved a strip-out of the existing plant room, including the removal of all redundant boilers, gas fired hot water cylinder, pumps, section of pipework, and associated services. 
 
Two (2no) Ideal Evomax 60kW condensing boilers were installed and connected to a common low-loss header, ensuring efficient load sharing and balanced flow rates across the boiler array. 
 
The boiler flue system was configured on a common header that utilised the existing flue hole, due to asbestos issues. 
 
New gas solenoid valve was installed in accordance with current gas safety regulations. This solenoid valve is interlocked with the controls for safe isolation in the event of fault or emergency. 
 
All existing pumps/pressurisation sets and valves have been re-used as per the clients specification. 
 
Modification of the existing panel to suit the new system also took place. This enabled the installation of a fully modernised, energy-efficient heating system. 